We work with our electricity transmission network operators, electricity distribution network operators and independent distribution network operators members and with government and Ofgem.
There is also an opportunity for selected customers, generators and manufacturers to participate in forums and workshops where technical issues can be raised and discussed with distribution network operators and peers.
The groups participating have the opportunity to review and understand specific challenges and to work together to resolve them, to provide or develop guidance and to liaise with regulator and government.
The specific programmes are revised and new ones developed as network management systems, processes and regulatory requirements evolve.
- Databases
- Resource library
- G99 Form B3
- G99 Form C2.1
- G99 Form C2.2
- G99 Form C3
- G99 Form D1
- G100 Appendix B
- Single Electric Vehicles and Heat Pumps Installation Application Form
- Angler Safety and Risk Assessment (30 m Angling Exclusion Zone)
- Angling Guidance Sheet
- Angler Safety and Risk Assessment (overhead power lines)
- Fish Safe A5 Flyer
- Fish Safe Sticker
- Angling Guidance for Anglers
- Angling Guidance for Management
- Angling Guidance for Planning Authorities
- Look Out, Look Up! Campaign Toolkit 2018
- Farmers & Agricultural Contractors Safety Advice
- Mechanical Plant Safety Advice
- Electricity Around Your Home Public Safety Leaflet
- Emergency Services Public Safety Leaflet
- General Trade and Maintenance Public Safety Leaflet
- Leisure Activities Public Safety Leaflet
- Look Out, Look Up! Public Safety Leaflet
- Watch Out, Cables About! Public Safety Leaflet
- Electric and Magnetic Fields Facts
- Electric and Magnetic Fields Information
- Electric and Magnetic Fields Networks Training
- Phasing of UK Overhead Power Lines Report
- Industry Health Outcomes National Survey
- Control of Electromagnetic Fields at Work Regulations 2016 (Risk Assessment)
- OHAG Guidance Note 1.1 Occupational Health in the Electricity Industry
- OHAG Guidance Note 1.2 Role of Occupational Health in Sickness Absence Management
- OHAG Guidance Note 1.3 Equality Act
- OHAG Guidance Note 1.4 Workplace rehabilitation
- OHAG Guidance Note 1.5 Automated External Defibrillators
- OHAG Guidance Note 1.6 Health surveillance
- OHAG Guidance Note 2.1 Stress
- OHAG Guidance Note 2.2 Management of back pain in the Electricity Industry
- OHAG Guidance Note 3.1 Working in Adverse thermal Environments
- OHAG Guidance Note 3.2 Working in confined spaces
- OHAG Guidance Note 3.3 Night work
- OHAG Guidance Note 3.4 Fitness to work at Heights
- OHAG Guidance Note 3.5 Fitness for Wind Turbine Working - web site
- OHAG Guidance Note 4.1 Noise and Vibration
- OHAG Guidance Note 4.2 Upper Limb Disorders
- OHAG Guidance Note 4.3 Biomass
- OHAG Guidance Note 4.4 Call Centre Working
- OHAG Guidance Note 4.5 Asthma in the Electricity Industry
- EMF - Design and Management of Low Voltage Distribution Networks Guidance (EREC G92)
- G98 Distributed Generation Connection Guide (Multiple Premises)
- G98 Distributed Generation Connection Guide (Single Premises)
- G98 Connecting Domestic-Scale Type Tested Generation Summary Guide (Single Premises)
- G99 Connecting Type A Power Generating Modules Guide
- G99 Connecting Type B - D Power Generating Modules Guide
- G99 Type A summary
- G99 Types B-D summary
- Open Networks 2018 PRJ-WS2-P3 Connection of Generation Terms and Definitions
- Open Networks Connection of Generation Guide
- Energy Delivery Systems Cyber Security Procurement Guidance
- Smart Meters - Electricity Network Operator Configurations (EREC M30)
- Smart Meters - How to Report Gas Asset Condition Issues (GER1)
- Smart Meters - How to Report Common Gas Issues (GER2)
- Smart Meters - Top 5 Gas Smart Meter Interventions (GER4)
- Smart Meters - Correct Reporting of Exposed PE Pipe (GER5)
- Open Networks 2018 WS3-Open Networks Models User Guide
- SAGE First Interim Assessment Guide
- Ecological and Archaeological Management Best Practice Guide
- Steel Lattice Tower Refurbishment Good Practice Guide
- ENA and Environment Agency Partnership Agreement
- Health and Wellbeing Framework
- Powering Improvement Occupational Health Delivery Plan 2010
- Cut-Out Rating Guidance to Electric Vehicles or Heat Pumps Installers
- Low Carbon Technologies User Guidance for Heat Pump Database Submission
- Switchgear Assessment Panel Notice of Conformity List
- Protection Assessment Panel Notice of Conformity List
- Electricity Supply Emergency Code
- Electric Vehicles and Heat Pumps Combined Installation Process Flow Chart
- Open Networks 2020 WS1B-P3 Process Diagram
- Accelerated Loss of Mains Change Programme Assessment Flow Chart
- Low Carbon Technologies Heat Pump Database
- Open Networks 2018 WS3 Least Regrets Tables
- Open Networks 2019 WS1B-P4 Enhanced Schedule 11
- Open Networks 2019 WS1B-P4 Schedule 5 Enhanced Node Data
- Open Networks DSO Implementation Plan Roadmap
- Open Networks Flexibility in Great Britain Timeline
- Low Carbon Technologies Heat Pump and Electric Vehicle Network Operator Contacts
- Open Networks 2017 WS2 Customer Information Requirements
- Open Networks 2017 WS2-P3 Customer Journey (New or Modified Connections)
- Open Networks 2017 WS2-P3 Customer Journey (Post-connection)
- Open Networks 2018 PRJ-DSO Service Requirements - Definitions
- Open Networks 2018 PRJ Product Definition
- Open Networks 2018 PRJ-WS2-P1 Pre Application Good Practice
- Open Networks 2018 WS1-P2 Workstream 1 Product Definitions
- Open Networks 2018 WS1-P3 Code Interactions Summary
- Open Networks 2019 PRJ PID Consultation Summary and Actions
- Open Networks 2019 PRJ Phase 3 2019 Consultation Document
- Open Networks 2019 PRJ-PHASE 3 PID
- Open Networks 2019 WS1A-Flexibility Consultation Paper
- Open Networks 2019 WS1A-P2 DSO Services Procurement Processes Consultation
- Open Networks 2019 WS2 Interactivity and Queue Management Consultation Document
- Open Networks 2019 WS2 Interactivity and Queue Management Consultation Summary and Response
- Open Networks 2019 WS2-P1 Information Sheet System Wide Resource Register
- Open Networks 2020 PRJ PID Consultation Webinar
- Open Networks 2020 PRJ Workplan Consultation Paper
- Open Networks 2020 PRJ-AG July Response
- Open Networks 2020 PRJ Flexibility Consultation Paper 2020
- Open Networks 2020 WS1A-P2 Flexibility Consultation Tender Timeline
- Open Networks 2020 WS1A-P3 Implementation Plan
- Open Networks 2020 WS1A-P3 Product Parameter Definitions
- Open Networks 2020 WS1A-P4 Standard Contract Implementation Plan
- Open Networks 2020 WS1A-P4 Standard Flexibility Services Agreement
- Open Networks 2020 WS1A-P4 Webinar slides
- Open Networks 2020 WS1A-P5 DSO Revenue Stacking
- Open Networks 2020 WS1A-P5 Webinar Slides (16 June 2020)
- Open Networks 2020 WS1A-P7 Detailed Product Scope
- Open Networks 2020 WS1A-P7-ITT Flexibility Consultation Baseline
- Open Networks 2020 WS1B-P2 July Update (31 July 2020)
- Open Networks 2020 WS2 Interactivity User Guide T_D interactivity pages July2020
- Open Networks 2020 WS2 Interactivity User Guide T_D Interactivity pages- 290420
- Open Networks 2020 WS2 Interactivity Webinar 20 July- 210720
- Open Networks 2020 WS2-P2 Queue Management Consultation Document
- Open Networks 2020 WS2-P3 Interactivity Webinar Q&A- 210720
- Open Networks 2020 WS2-QM Consultation Webinar 20th May- 210520
- Open Networks 2020 WS3-P5 Introductory Slides
- Open Networks 2020 WS5-DSO Implementation Plan Webinar Slides- 170720
- Open Networks Flexibility Commitment 2018
- Open Networks Flexibility Commitment 2019
- ALoMCP Public Issues Log
- ALoMCP General FAQs
- ALoMCP Contractual Terms and Conditions
- ALoMCP Delivery Assurance Policy
- ALoMCP Payment Process Specification
- ALoMCP Technical FAQs
- ALoMCP Protection Support Organisations
- Open Networks 2021 WS3-P1 DSO Implementation Plan Appendices (31 Mar 2021)
- Open Networks 2019 PRJ-Workplan Consultation Responses
- Open Networks 2019 WS2 Interactivity & Queue Management Consultation Responses
- Open Networks 2020 WS1A-P1 CBA Templates
- Open Networks 2019 WS3 Final Future World results
- Open Networks 2019 WS3 Final Future World results - Sensitivity
- Open Networks 2019 WS3 Impact Assessment on Future DSO Worlds (Benefits)
- Open Networks 2019 WS3 Integrated World Costs
- Open Networks 2019 WS3 Impact Assessment on Future DSO Worlds (Costs)
- Smart Meters - Benefits for Demand Response Based Control of Distribution Networks
- Smart Meters - Data Aggregation Benefits Reduction
- Smart Meters - Data Aggregation Executive Summary
- Smart Meters - Data Aggregation Assessment Final Report
- Smart Meters - Functional Requirements for Electricity Smart Meters
- Smart Meters - High Level Cost Benefit Analysis Summary
- Smart Meters - High Level Cost Benefit Analysis
- Smart Meters - High Level Data Traffic Analysis
- Smart Meters - Consumer Attitudes to Half Hourly Consumption Data
- Smart Meters - Opportunities for Demand Response
- Smart Meters - Strategic Issues and Action Planning for Demand Response
- Smart Meters - Privacy Impact Assessment of Networks Using Smart Meter Data
- Smart Meters - Security and Privacy Control Points
- Smart Meters - System Use Cases
- Trading of Non-firm DG Curtailment Obligations & Exchange of Access Rights Report
- Open Networks 2017 PRJ End of Year Report
- Open Networks 2017 WS1-P1 Key Learnings Trail Projects
- Open Networks 2017 WS1-P1 Mapping TO, SO and DNO processes
- Open Networks 2017 WS1-P2 Gaps Issues Report
- Open Networks 2017 WS1-P3 Investment Planning Model (Short Term)
- Open Networks 2017 WS1-P5 Coordination in an Operational Timeframe
- Open Networks 2017 WS1-P5 Curtailment Assessment Process
- Open Networks 2017 WS1-P5 Report on Potential Conflicts
- Open Networks 2017 WS1-P7 GSP Planning Limit Roll Out Programme
- Open Networks 2017 WS1-P7 Statement of Works Customer Journey
- Open Networks 2017 WS1-P7 Statement of Works Data Template
- Open Networks 2017 WS2 Customer Category Descriptions
- Open Networks 2017 WS2 Information on Distribution Connection Options
- Open Networks 2017 WS4-Product Summary
- Open Networks 2018 PRJ End of year Report
- Open Networks 2018 PRJ End of Year Report Summary
- Open Networks 2018 PRJ Phase 2 Project Initiation Document Post-Consultation
- Open Networks 2018 WS1-P1 Investment Planning Processes and Approach
- Open Networks 2018 WS1-P1 Regional Development Plan Learnings
- Open Networks 2018 WS1-P11 Flexible Resources Connection Guide
- Open Networks 2018 WS1-P12.1 Review of Key Learnings
- Open Networks 2018 WS1-P13 Interim Report
- Open Networks 2018 WS1-P13.2 Review of Key Learnings_June2018
- Open Networks 2018 WS1-P2 DSO Service Requirements - Definitions
- Open Networks 2018 WS1-P2 DSOService_E2E_Process_WS1
- Open Networks 2018 WS1-P2 Review of Key Learnings
- Open Networks 2018 WS1-P4 SQSS P2 Review
- Open Networks 2018 WS1-P4 Whole System Operability Progress
- Open Networks 2018 WS1-P4 Reliability Standards & Emergency Requirements
- Open Networks 2018 WS1-P5 Whole System FES Report
- Open Networks 2018 WS1-P5.1 Review of Current Forecasting Approaches
- Open Networks 2018 WS1-P7 Good Practice Guide
- Open Networks 2018 WS1-P8 System Wide Resource Register Feasibility Report
- Open Networks 2018 WS1-P8 System Wide Resource Register
- Open Networks 2018 WS2-P1 Pre Application Good Practice
- Open Networks 2018 WS2-P3 P3 Terms and Definitions
- Open Networks 2018 WS2-P3 Updated Terms and Definitions (Sep 19)
- Open Networks 2018 WS2-P4 Good Practice FLEXIBILITY SERVICES
- Open Networks 2018 WS2-P6 Good Practice POST CONNECTION
- Open Networks 2018 WS2-P7 Provision of Constraint Information
- Open Networks 2018 WS3-DSO Definition (updated)
- Open Networks 2018 WS3-Least Regrets Analysis 2019 PID Input
- Open Networks 2018 WS3-Modelling-DSO-Transition-Using-SGAM_Issue2.1_PublicDomain
- Open Networks 2018 WS3-P2 DSO Functional Requirements
- Open Networks 2019 PRJ End of Year Report
- Open Networks 2019 PRJ Monitoring Implementation (Q2 2019)
- Open Networks 2019 PRJ Monitoring Implementation (Q4 2019)
- Open Networks 2019 PRJ Phase 3 PID Post-Consultation
- Open Networks 2019 PRJ Open Letter to Ofgem BEIS
- Open Networks 2019 WS1A-P5 ANM Flex Stackability
- Open Networks 2019 WS1A-P1 Flexibility Market Principles
- Open Networks 2019 WS1A-P2 DSO Services Procurement Processes Dec 19 Update
- Open Networks 2019 WS1A-P2 DSOServices Procurement Processes Consultation
- Open Networks 2019 WS1A-P3 Dispatch Settlement Processes
- Open Networks 2019 WS1A-P5 Final Report
- Open Networks 2019 WS1A-P6 Facilitation of New Markets Final
- Open Networks 2019 WS1A Workshop Response
- Open Networks 2019 WS1B-P2 Scenarios Publication Timeline
- Open Networks 2019 WS1B-P2 Whole Systems FES End of Year Report
- Open Networks 2019 WS1B-P3 Final Report
- Open Networks 2019 WS1B-P4 Data Exchange Report
- Open Networks 2019 WS1B-P4 Data Scope - Final Report
- Open Networks 2019 WS2-P2 Queue Management - Examples
- Open Networks 2019 WS2-P2 Queue Management Implementation Plan
- Open Networks 2019 WS2-P3 Implementation Plan for GB Common Interactivity Process
- Open Networks 2019 WS3-Baringa Future World Impact Assessment Report
- Open Networks 2019 WS3-Future World Impact Assessment Report
- Open Networks 2019 WS3-P7 Update on Least Regrets Analysis
- Open Networks 2019 WS4-Final Report
- Open Networks 2019 WS4-Interim Report
- Open Networks 2020 PRJ-2020 PID Consultation Detailed Comments and Responses
- Open Networks 2020 PRJ-2020 Workplan Consultation Summary
- Open Networks 2020 PRJ-Phase 4 PID Post-Consultation
- Open Networks 2020 PRJ-Phase 4 PID Pre-Consultation
- Open Networks 2020 WS1A-P2 Existing Processes
- Open Networks 2020 WS1A-P4 CMS Updated Contract Summary
- Open Networks 2020 WS1B-P3 Operational Tripping Schemes Requirements
- Open Networks 2020 WS1B-P5 Final Report on Network Capacity Indications Survey
- Open Networks 2020 WS2-P3 Interactivity User Guide
- Open Networks 2020 WS3-Innovation Trials Final Report
- Open Networks 2020 WS3-P1 DSO Implementation Roadmap Guide
- Open Networks 2020 WS4-P1 Report
- Open Networks 2020 WS4-P3 Phase 1 Report
- Open Networks 2020 WS4-P5 Coordinated Regional Data Gathering Final Report
- Open Networks 2020 WS4-P6 Capacity Data-Mapping
- Public Safety Annual Review 2019
- SAGE First Interim Assessment Precautionary Approaches to ELF EMFs
- Health and Safety Issues Eurelectric Report 2014
- Health & Wellbeing Framework Position Paper 2017
- Open Networks 2020 WS2-P3 Interactivity Go Live 2020 Dates
- Smart Meters - System Requirements Update
- Open Networks 2018 WS1-P1 Investment Planning Roadmap
- Smart Meters - Data Traffic Analysis
- Gas and Electricity Network Innovation Strategy 2020 (Summary)
- Electricity Network Innovation Strategy 2020
- Gas Network Innovation Strategy 2020
- Electricity Network Innovation Strategy 2018
- Gas Network Innovation Strategy 2018 (Summary)
- Gas Network Innovation Strategy 2018
- Networks Innovation Strategies 2020 Stakeholder Engagement (Survey)
- Networks Innovation Strategies 2020 Stakeholder Engagement (Workshop)
- ENA Public Safety Commitment 2020-2022
- Powering Improvement Industry Strategy 2020-2025
- Gas Goes Green Launch Document - April 2020
- Gas Goes Green Advisory Group May 2020 - Meeting Slides
- Gas Goes Green Advisory Group May 2020 - Minutes
- Gas Goes Green Advisory Group May 2020 - Poll Results
- Gas Goes Green Advisory Group May 2020 - Responses to Questions
- Gas Goes Green Advisory Group Terms of Reference
- Gas Goes Green webinar on the Green Gas Support Scheme - slides
- Gas Goes Green webinar on the Green Gas Support Scheme - Questions
- Gas Goes Green Zero Carbon Commitment - May 2020
- Gas Goes Green Hydrogen Cost to Customer Report - May 2020
- Gas Goes Green webinar supporting IGEM’s peer review consultation for gas quality and changes to GS(M)R - slides
- Gas Goes Green Webinar supporting IGEM’s peer review consultation for gas quality and changes to GS(M)R - responses
- Gas Goes Green webinar exploring hydrogen deblending - slides
- Gas Goes Green webinar exploring hydrogen deblending - speaker biographies
- Gas Goes Green webinar exploring hydrogen deblending - poll results
- Pathways to Net Zero: Decarbonising the Gas Networks in Great Britain
- Network Hydrogen 2020 Project Updates (Mar)
- Network Hydrogen 2020 Project Updates (Apr)
- Network Hydrogen 2020 Project Updates (Jul)
- GIS/14525 Flanged Adaptors and Mechanical Couplings DN50 to DN600 and Up to 2 Bar
- GIS/C5 Distribution Pipe Fittings Cast In Grey Cast Iron for Use Up to 7 Bar
- GIS/C6:2006 Specification for Distribution Pipe Fittings Cast In Ductile Iron for Use Up to 7 Bar Maximum Operating Pressures
- GIS/C8:2006 Specification for Distribution Split Tee and Collar Pipe Fittings Cast In Grey Or Ductile Iron Up to 7 Bar Maximum Operating Pressures
- GIS/E1:2006 Specification for combined drilling, tapping and service fitting insertion machines for use up to 2 bar
- GIS/E13 Part 1:2019 Gas Filters (80mm Nominal Size and Above) Suitable for Use In the Pressure Range
- GIS/E17 Part 2 Insulation Joints Part 2 - Joints Operating At Pressures Not Greater Than 7 Bar
- GIS/E19:2006 Specification for the design, performance and material requirements for inflatable bags for use in the primary (iris supported) position of an iris stop system
- GIS/E20 Secondary Iris Stop Bags
- GIS/E22:2006 Specification for vehicle-mounted leakage survey equipment — minimum performance and maintenance requirements for equipment used for winter and trigger surveys
- GIS/E4 Inflatable, Self-Centring Bag Stoppers for Use On Distribution Mains
- GIS/E48:2006 Specification for polyethylene (PE) service line tracing equipment purchased or hired for use by the gas transporter
- GIS/E49:2019 Specification for polyethylene (PE) coil trailers, including polyethylene pipe coil trailers capable of safely storing, transporting and dispensing pipe in the
- GIS/E5 Pipe Cutting Wheels for Hand-Operated Wheeled Pipe Cutters
- GIS/E58:2006 Specification for Gland Seals for Insertion of Polyethylene Pipe Into Low Pressure Metallic Gas Mains
- GIS/E59:2006 Specification for Foam Plug Flow Stop Devices for LP and MP Gas Mains and Services
- GIS/E6 Vaporizers and Foggers for Joint Sealing On Gas Mains
- GIS/ECE1 Electrofusion Control Boxes
- GIS/EFV1:2006 Flow limiters for polyethylene services operating at pressures above 75 Mbar and not exceeding 2.0 bar and for gas flows not exceeding 6 m3h-1
- GIS/EL8:2006 Specification for the Manufacture of Gasholder Modular Antifreeze Units
- GIS/F13 Ductile Iron and Fabricated Steel Cap Ends for Use Up to 2bar MOP
- GIS/F16:2006 Specification for In-Pipe Close Fit Lined Pipe Service Fittings
- GIS/F17 In-Pipe Close Fit Lined Mains Connection Fittings
- GIS/F2 Main Sealing Plugs and Service Connection Fittings Not Greater Than 2 Bar
- GIS/F7 Steel Welding Pipe Fittings 15mm to 450mm Not Greater Than 7 Bar
- GIS/F9:2020 Metric and Imperial Stainless Steel Single and Twin Ferrule Compression Fittings
- GIS/GQ7 Equipment for Odour Intensity Monitoring
- GIS/L2 Steelpipe 21.3 mm to 1219 mm Outside Diameter Up to 7 Bar (Supplementary)
- GIS/LC1:2018 Leak Repair and Annular Sealants for Metallic Gas Mains and Services Up to 7bar
- GIS/LC12 Sealant Systems for Joint Repair on Metallic Distribution Pipe Systems (Minor Roads and Footpaths)
- GIS/LC14 Annular Gap Sealants
- GIS/LC25 External Sealant Injection Systems for Joint Repair on Metallic Distribution Pipe 2 Bar or Less
- GIS/LC8 Part 1 Methods of Repairing Leaking Ferrous Gas Mains Part 1 - External Systems
- GIS/LC8 Part 3 Methods of Repairing Leaking Ferrous Gas Mains Part 3 - Internal Sealing Methods
- GIS/LC8 Part 4 Methods of Repairing Leaking Ferrous Gas Mains Part 4 - Clamps, Collars and Branch Connections
- GIS/LC9 Methods of Repairing Joints On Screwed Pipework
- GIS/PL2 - 5 Polyethylene Pipes and Fittings for Gas Part 5 - Electrofusion Ancillary Tooling
- GIS/PL2 Part 2 Polyethylene Pipes and Fittings for Gas Part 2 - Pipes Up to 5.5 Bar
- GIS/PL2 Part 3 Polyethylene Pipes and Fittings for Gas Part 3 - Butt Fusion Tooling and Ancillary Equipment
- GIS/PL2 Part 4 Polyethylene Pipes and Fittings for Gas Part 4 - Fusion Fittings with Integral Heating Element(s)
- GIS/PL2 Part 6 Polyethylene Pipes and Fittings for Gas Part 6 - Spigot End Fittings
- GIS/PL2 Part 7 Polyethylene Pipes and Fittings for Gas Part 7 - Squeeze-Off Tools and Equipment
- GIS/PL2 Part 8 Polyethylene Pipes and Fittings for Gas Part 8 - Pipes Up to 7 Bar
- GIS/PL2-1 Polyethylene Pipes and Fittings for Gas Part 1 - General & PE Compounds
- GIS/PL2-9:2019 Polyethylene Pipes and Fittings for Natural Gas and Suitable Manufactured Gas
- GIS/PL3 Self Anchoring Mechanical Fittings for Polyethylene Pipe for Gas
- GIS/PL4 Part 1 Elastomeric Diaphragms Part 1 - Homogeneous Diaphragms
- GIS/PRS35 GRP Housings for Gas Regulator Installations and Associated Operation Equipment
- GIS/SER6 Live Riser Transfer Technique
- GIS/TE D 1-2 Non-Tap Mains Sealing Plugs for Use In Access Holes
- GIS/TE D 1-3 Holesaws and Holesaw Taps for Use On Gas Pipes Not Greater Than 2 Bar
- GIS/TE/E1.9 Live Mains Abandonment Equipment for Low Pressure Mains
- GIS/TEE1.7 Tooling for the Removal of Caps and Plugs From Live Low Pressure Services
- GIS/TEE1.8 Access Tool for Live Entry Into A Low Pressure Polyethylene Service
- GIS/TEP6.1 Bypass Equipment with Integral Pressure Monitoring Points for MP PE Mains
- GIS/TEP6.3 Equipment Used In Testing Gas Mains and Gas Services Not Greater Than 7 Bar
- GIS/V12 Sealant Replacement for Valves Operating Up to and Including 2 Bar
- GIS/V4 Service Isolation Valves Up to 50 mm Diameter Up to 2 Bar
- GIS/V7 Part 1 Distribution Valves Part 1 - Metal-Bodied Line Valves and Construction Valves
- GIS/V7 Part 2 Distribution Valves Part 2 - Plastics Bodied Valves
- GIS/V7 Part 3 Distribution Valves Part 3 - Brass Bodied Manually Operated Ball and Taper Plug Valves
- GIS/V9 Part 1 Slamshut Valves for Governor Installations with Inlet Pressures (Spring Operated Diaphragm Type)
- Network Operator Common Network Asset Indices Methodology
- Common Network Asset Indices Methodology Proposed Modifications for RIIO-ED2
- Proposed CNAIM Methodology Changes Explained
- SHE 2019 Presentation Conference Keynote
- SHE 2019 Presentation Human Factors – Company view
- SHE 2019 Presentation Human Factors – Trade Union view
- SHE 2019 Presentation Powering Improvement 2019 – HSL Research Study
- SHE 2019 Presentation Training & Skills
- SHE 2019 Presentation Safety Culture & Behaviours
- SHE 2019 Presentation Environmental Management
- SHE 2019 Presentation Caithness-Moray Project
- SHE 2019 Presentation Public Safety – Organisational Response
- SHE 2019 Presentation Occupational Health – Good Business Sense
- SHE 2019 Presentation Balfour Beatty Transmission & Distribution Project
- SHE 2019 Presentation DSO & Innovation
- SHE 2019 Presentation DSO & Innovation 2
- Guide to the SAGE First Interim Assessment
- Control of Electromagnetic Fields at Work Regulations 2016
- Electric and Magnetic Fields (EMFs) website
- New Exposure Limits Training Video for Electric and Magnetic Fields (EMFs)
- Equipment interventions
- Engineering and technical programmes
- Standards and guidance
- Statutory information