SP Energy Networks

Check the table below to see what information SP Energy Networks publish and where you can find it. The 2 data sources are SP Energy Networks’ Long Term Development Statement (LTDS) and the Embedded Register maintained by the National Grid ESO. For the LTDS, if you have not previously registered with SP Energy Networks, you will need to register to access information.

Data ItemDescriptionAvailable?Source?Registration required?Comments
           
SPEN Distributed Energy Resources Information          
Customer Name Name of party contracted to connect. Yes (SPD) NGESO Embedded Register No Available for SP Distribution in NGESO Embedded Register.
Customer / Project Site Name of customer site/project name. Yes LTDS, NGESO Embedded Register LTDS requires registration. As above
Connection Site (GSP) Grid Supply Point linked with Customer Site. Yes LTDS, NGESO Embedded Register LTDS requires registration. As above
Supply Point Electrical position where the customer equipment connects to the distribution network. Yes LTDS, NGESO Embedded Register LTDS requires registration. As above
Primary Name of relevant primary substation. Yes LTDS, NGESO Embedded Register LTDS requires registration. As above
MW Connected Total MW connected at Project Site. Yes LTDS, NGESO Embedded Register LTDS requires registration. As above
MW Contracted Total MW contracted in Construction Offer. Yes LTDS, NGESO Embedded Register LTDS requires registration. As above
Export MW Capacity Total MW capacity permitted as per connection agreement. Yes LTDS, NGESO Embedded Register LTDS requires registration. As above
Date Contracted Date customer contracted. No      
Date Connected Date Project connected to network. Yes NGESO Embedded Register. No Available for SP Distribution in NGESO Embedded Register.
Status Connected, Being Built, Contracted. Yes NGESO Embedded Register. No As above
Licence Area Licence area project site is connected within. Yes LTDS, NGESO Embedded Register LTDS requires registration. As above
Plant Type Type of plant connected at the site (wind/solar/etc). Yes LTDS, NGESO Embedded Register LTDS requires registration. As above
           
SPEN Works Register Queue Information          
           
Data Item Description Available? Source? Registration required? Comments
Works Reference Reinforcement Reference Number Yes (SPM) LTDS LTDS requires registration. SP Manweb Only for Distribution
Works Description Reinforcement Title/Summary Description Yes LTDS LTDS requires registration.  
Works Completion Date Planned Completion Date of Works Yes (SPM) LTDS LTDS requires registration. SP Manweb Only for Distribution
Driver (Generation/Demand) Are works driven by demand or generation? No      
Licence Area Licence area where works will be delivered Yes LTDS LTDS requires registration.  
T/D Transmission or Distribution Yes LTDS LTDS requires registration.  
Customer Site Name of customer site/project No      
GSP Grid Supply Point linked with Customer Site No      
Customer Completion Date Completion date of customer connection No